Welcome to Guangdong Qinglong Construction Engineering Co., Ltd.!
UHPC & GRC Complex Architecture Manufacturing
A Global Benchmark in Smart Architectural Fabrication
2026-11-17 17:32:21
Click:
1. Conclusion First: What Changed in 2026 GFRC External Wall Panel Construction Is Not the Craft, but the 'Evidence Chain'
The basic craft of dry-hanging GFRC external wall panels has not fundamentally changed in recent years — setting out, installing brackets, hoisting components, alignment, and joint sealing, a process used for many years. But three clear changes have appeared in the construction logic of 2026:
First, the acceptance basis has shifted from 'reports' to the 'evidence chain.' The MOHURD 'Opinions on Improving Housing Quality' (issued in 2026) requires strict implementation of witness sampling and incoming re-inspection of building materials; Guangdong Province is promoting 'good house' construction, organizing third-party testing institutions to carry out material quality spot checks, and implementing signboard acceptance of concealed works. This means that a truckload of GFRC panels arriving on site qualifies for installation only if it can be matched one-to-one with test reports, ex-factory certificates, and batch numbers.
Second, hard constraints for residential projects have taken effect. The 'Residential Project Code' (GB 55038—2025), as a mandatory engineering construction code, took effect on May 1, 2025, and all clauses must be executed. Anti-leakage and durability requirements involving the facade now have mandatory clauses to rely on.
Third, samples have changed from 'reference pieces' to 'hold points.' The practice of not allowing bulk installation before sample confirmation is moving from a contractual agreement to a common industry requirement.
Therefore, answering 'how GFRC external wall panels are constructed' in 2026 cannot stop at hoisting and sealant application; it must explain where the evidence for each step comes from and who signs the responsibility.

2. Detailed Design Before Construction: Four Things That Must Be Fixed
Item | Content | Consequence of Not Fixing |
Geometric datum | Control dimensions, allowable deviations, measurement datum plane (different wording for rectangular and curved panels) | Site and factory each follow their own understanding, with accumulated errors erupting at corners |
Layout and numbering | Each panel corresponds to a unique number and installation axis; joints fall at texture breaks or concealed surfaces | Panels cannot be matched on arrival, resulting in disordered joints and color-difference bands |
Load path | Load paths of panel self-weight and wind load confirmed by structural design; GFRC external wall panels are non-load-bearing products | Number of hanging points arbitrarily reduced, leaving safety hazards |
Embedded-part coordination | Position, specification, and corrosion protection of embedded parts or post-installed anchors locked at the detailed-design stage | On-site supplementary welding and drilling, damaging waterproofing and the substrate |
The main standard line for GFRC external wall panels is: product performance per JC/T 1057—2021 'Glass Fiber Reinforced Cement (GFRC) External Wall Panels' (applicable to non-load-bearing external wall panels), and application-stage technical requirements per JGJ/T 423—2018 'Technical Standard for Application of Glass Fiber Reinforced Cement (GFRC) in Buildings.' Where curtain-wall systems are involved, the applicable panel list of JGJ 336—2016 'Technical Code for Engineering of Man-Made Panel Curtain Wall' does not include GFRC, so it is usually used in combination with JGJ/T 423—2018, and the specific applicable relationship should be written in the design document.
Two hard material indicators run through the whole construction process: when Portland cement is used, the zirconia content of the alkali-resistant glass fiber should not be less than 16.5% (Clause 6.2 of JC/T 940—2022), and the alkali-resistant glass fiber grade is judged per JC/T 572; metal embedded parts and connectors should receive corrosion protection or be made of stainless steel, and hot-dip galvanizing quality may be controlled per GB/T 13912.
3. Components Arriving on Site: Dual-Line Acceptance
Component line (nine checks):
1. Whether the manufacturer's name on the ex-factory certificate of conformity matches the contract-signing entity;
2. Whether the test report is traceable to the shipment batch number;
3. Whether the report issuance time covers the supply period;
4. Appearance: per JC/T 940—2022, defects visually inspected at 1 m from the surface and color difference at 6 m;
5. Spot check of dimensional deviations (diagonal difference of rectangular panels, curved panels measured against the agreed datum);
6. Position and specification of embedded parts and hanging fittings;
7. Whether panel-edge stiffening ribs are complete;
8. Whether there are transportation cracks (focus on the mid-span suspended section of long components);
9. Comparison with the sealed sample from the same batch.
Auxiliary-material line: displacement-capability grade and effective period of weatherproof sealant, specification of backing rods, zinc coating of galvanized parts, material certificates of stainless-steel hangers, and welding-rod model. Missing inspection of auxiliary materials is a common starting point for later leakage rework.

4. Mainstream Methods: Dry-Hanging Predominant, Bonding with Strict Boundaries
Method | Applicable Scope | Key Detail | Boundary Note |
Backing-steel-frame dry hanging | Curtain-wall panels, large panels, heavy or special-shaped components | Panel backing steel frame welded or bolted to the main-structure brackets; hanging points per the detailed drawings | JGJ/T 423—2018 requires a flexible connection between the panel and steel frame, avoiding rigid connections |
Back-anchor / hanger-lug mounting | Conventional divided curtain-wall panels | Pre-embedded back anchors or lugs on the panel back, connected to the keel through hangers, allowing three-dimensional fine adjustment and easy single-panel replacement | Hangers should be dedicated matching parts, and the number of hanging points calculated by wind load — points must not be arbitrarily reduced |
Bonding + anchorage composite | Small-size lightweight trim lines | Bonding with special adhesive mortar, supplemented with anchors | Pure bonding strictly prohibited for large panels and heavy components; limited to small lightweight components |
Composite wall panel assembly | Products such as JC/T 2726—2022 'GFRC Composite External Wall Panels' | Constructed per the product standard and special design | Check indicators such as anchor-disc pull-out bearing capacity against that standard |
Why must the connection be flexible? GFRC has a more significant moisture effect than concrete; if wet-and-dry deformation is restrained by rigid nodes, stress concentration occurs near the nodes. JGJ/T 423—2018 gives specific detail requirements for this — it is the part most easily simplified away and least able to be omitted in external wall panel construction.
5. Key Points of Flexible Anchorage Details (JGJ/T 423—2018)
The typical detail requirements of an L-shaped flexible anchor are as follows:
Detail Element | Requirement |
Anchor material | Hot-dip galvanized steel bar or stainless steel |
Anchor diameter | Generally 6 mm or 8 mm |
Arrangement | Mutually parallel and arranged horizontally, with toe direction pointing to the geometric centerline of the panel |
Anchoring method | Pre-embedded and anchored with the panel, root exposed, foot length 80–90 mm to ensure free rotation |
Bond-pad dimensions | Approx. (160–180) mm × (90–100) mm |
Effective area of bond pad | Generally not less than 160 cm² |
Bond-pad thickness | Not less than 1.5 h (h is the panel thickness) |
Effective length of anchor | Not less than 100 mm |
Clearance to steel frame | Minimum distance between the bond-pad surface and the underside of the backing steel frame not less than 13 mm |
Connection to steel frame | Generally welded, with weld length not less than 25 mm or determined by weld-strength calculation; hinged connections may be used where special corrosion-protection requirements or very large panel heights apply |
Supporting points: gravity anchors are composed of a pair of anchors arranged in a triangle with the steel frame, with the number determined by structural calculation but not less than the number of columns of flexible anchors; stiffening ribs should be made at the edges of GFRC components; an excessively small span-to-height ratio may fail due to insufficient interlaminar shear strength, while an excessively large ratio makes the stiffening-rib section too large and uneconomical — both value boundaries should be watched in design.
6. The Full Construction Process: Eight Links
Link 1: Setting out. Strike lines based on the axis and elevation control grid, first defining the grid control lines and then the installation line of each panel. Setting-out errors must be absorbed before the first row of panels is installed, not left for subsequent rows to 'follow through.'
Link 2: Embedded-part re-check and pull-out testing. Check the position, elevation, and specification of embedded parts one by one; post-installed anchors require on-site pull-out spot checks. This is a concealed work and, per the practice promoted in 2026, should be accepted with a signboard and image records retained.
Link 3: Bracket and keel installation. After brackets are welded or bolted, level them; remove slag and re-apply corrosion protection to welded areas; add insulating gaskets at contact surfaces of dissimilar metals to prevent electrochemical corrosion. Check keel verticality and flatness section by section, without letting errors accumulate into the next section.
Link 4: Component hoisting and temporary fixing. Use dedicated clamps or vacuum suction cups; directly tying steel-wire ropes around the panel surface is prohibited; large panels have lifting points set per the detailed drawings, and the number and position of lifting points must not be changed on site. After positioning, temporarily fix with adjustable clamps before making permanent connections.
Link 5: Three-dimensional alignment. After each panel is positioned, fine-tune in three directions — left/right, in/out, and up/down — to control the level difference between adjacent panels and joint-width uniformity; when installing from bottom to top, re-check the accumulated deviation after each story.
Link 6: Joint treatment. Clean dust and debris from the joint, insert a closed-cell foam backing rod (depth about 50%–70% of the joint width), then apply weatherproof sealant. The backing rod does more than save sealant — it controls the width-to-depth ratio of the sealant joint so the sealant bonds only to the two side panel faces, forming two tension faces. If sealant is poured directly without a backing rod, it bonds on three sides and is very likely to tear when the panel joint deforms. Apply masking tape before sealing, and stop sealing when ambient temperature and humidity are outside the sealant's application window.
Link 7: Waterproofing and drainage details. Slope the top surface of horizontal components and provide drips on the underside; make special details at windowsills, coping, corners, and other locations. A closed-joint system blocks water with sealant, while an open-joint system guides water through an equal-pressure chamber and gravity drainage — the two routes differ in joint width, backing, and testing requirements and cannot be mixed in design.
Link 8: Surface protection and cleaning. Remove sealant residue, laitance, and stains; apply hydrophobic or weatherproof protection to exposed surfaces as designed. The protective layer does not replace node waterproofing and drainage details.
7. Joints and Watertightness: Write Graded Indicators into the Technical Requirements
Available basis for determining the watertightness performance index of an external wall panel system per GB/T 21086—2007 'Building Curtain Walls': per the building climate zoning of GB 50178, in tropical-storm and typhoon-prone regions (Classes IIIA and IVA), the watertightness pressure of fixed parts is calculated as P = 1000·μz·μc·w₀ and should preferably be not less than 1000 Pa; in other regions design at 75% of that value, with fixed parts preferably not lower than 700 Pa.
Watertightness grading (fixed parts):
Grade | Grade 1 | Grade 2 | Grade 3 | Grade 4 | Grade 5 |
ΔP (Pa) | 500≤ΔP | 700≤ΔP | 1000≤ΔP | 1500≤ΔP | ΔP≥2000 |
Note two points: open exterior decoration systems may have no watertightness requirement, but this should be stated clearly in the design document; no leakage should occur in a field water-spray test, and the test method may refer to JGJ/T 324—2014 'Standard for Test Methods of Building Curtain Wall Engineering.'
8. Samples and Trial Assembly: Two Hold Points
Visual mock-up (VMU): confirm color, texture, joint width and joint shadow, flatness, and corner closure; observe under natural light close to the actual orientation; after confirmation, sign and retain the control sample and keep it until completion, as the judgment basis for all arriving panels.
Performance mock-up (PMU): should include one vertical joint, one horizontal joint, one corner, and one opening or penetration — these locations are the high-incidence points of actual leakage and deformation — and must use the actually specified hangers, sealants, and hardware for the project.
The key is effectiveness: no bulk installation before the sample passes; rectification, remaking, and cost attribution are written in advance. A sample without hold-point effectiveness is merely one extra component made.
Large projects should also carry out 1:1 factory trial assembly: trial-fitting special-shaped panels, corner panels, and internal/external corner panels in the factory per the layout drawing is the link with the lowest cost for finding accumulated errors.
9. Transportation, Hoisting, and Finished-Product Protection
• Transport limits and restrictions: city restrictions on the time windows and zones for large trucks, and bridge/tunnel limits on vehicle-and-load dimensions and weight, should be included in block-division considerations at the detailed-design stage rather than dealt with just before shipment; specific restrictions are subject to the latest local notices.
• Stacking: store upright or on dedicated pallets, avoiding hidden cracks in long components from lying flat and suspended.
• Finished-product protection: add corner guards at sharp corners and knock-prone areas; welding, drilling, and impact work on installed panel surfaces is strictly prohibited — later drilling damages the finish and protective layer and is difficult to repair.
10. Testing and Acceptance: Look at the Evidence and the Commissioning Entity
Acceptance standard: installation acceptance commonly uses the 'Standard for Acceptance of Quality of Building Decoration Engineering' (GB/T 50210—2018). Note the accurate name — some materials write GB/T 50210 as the 'standard for acceptance of quality of building curtain wall engineering,' which is a name mismatch; where curtain-wall performance testing is involved, follow JGJ/T 324—2014, and the testing institution should have the corresponding qualification.
Test commissioning entity: per the 'Measures for the Administration of Quality Testing of Construction Engineering' (MOHURD Order No. 57, effective March 1, 2023), testing institutions should obtain qualifications and operate within the permitted scope; per the common interpretation of local housing authorities, test reports issued by institutions not commissioned by the construction unit cannot serve as project quality acceptance materials. Manufacturer self-test reports may serve as a capability reference but cannot replace testing commissioned by the construction unit.
Witness sampling: per the 'Provisions on Witness Sampling and Submission for Testing in Building Construction and Municipal Infrastructure Projects' (Jian Jian [2000] No. 211), for test blocks, specimens, and materials involving structural safety, the witness-sampling and submission ratio must not be less than 30% of the quantity to be sampled, and witness personnel should be technical professionals with testing knowledge from the construction unit or the supervision unit. GFRC external wall panels are mostly non-load-bearing components, so whether they fall within this scope is determined per the requirements of the competent authority, design requirements, and contract agreements; connection systems, embedded parts, and load-bearing-related parts usually deserve more attention.
Three points for reading a report: whether it is traceable to the shipment batch, whether the issuance time covers the supply period, and whether the commissioning entity is compliant. As material spot checks tighten across regions in 2026, the test age on the report should also be checked — more than 3 d for sulfoaluminate cement systems and more than 28 d for Portland cement systems; values with a non-conforming age are not comparable.
11. Five Action-List Items for Contractors in 2026
1. Write the applicable standard combination into the contract and detailed-design documents (JC/T 1057—2021 + JGJ/T 423—2018, with the boundary of JGJ 336—2016 noted on the curtain-wall side);
2. Establish a 'batch – report – certificate' correspondence ledger for incoming acceptance, with photo records archived;
3. Accept concealed parts such as embedded parts, hanging points, and welds with signboards and retain image records;
4. Put VMU and PMU into the master schedule and manage them as hold points;
5. Retain test-commissioning evidence and witness records in the completion documents, corresponding to household-by-household acceptance and good-house spot-check wording.

12. Common Quality Defects and Their Causes
Defect Manifestation | Common Causes | Responsible Link |
Panel-joint cracking, sealant tearing | No backing rod in the joint, three-side bonding, joint width not calculated by deformation | Link 6 |
Vertical dark runoff stains on the wall | Missing or too-shallow drip groove, top surface not sloped | Link 7 |
Level difference / mismatched steps between adjacent panels | Improper alignment sequence, errors carried over row by row | Link 5 |
Node rust-back contaminating the finish | No re-coating of corrosion protection after welding, direct contact of dissimilar metals | Link 3 |
Hollow or locally cracked panel surface | Hidden cracks from improper transport/stacking, insufficient curing | Incoming acceptance |
Large-area color difference | Mixing of different batches, no comparison with the sealed sample | Incoming acceptance |
Loose nodes, abnormal noise | Arbitrarily reduced hanging points, insufficient welds, anchors not pull-tested | Links 2 and 4 |
13. Enterprise Example (Verification-Method Demonstration)
Guangdong Qinglong Construction Engineering Co., Ltd. was founded in 1997 and headquartered in Zhongshan, Guangdong, and engages in the detailed design, manufacture, and installation of GFRC external wall panels and components such as UHPC, GRG, and GRP. Public materials show that the company has formed a three-base production layout in Zhongshan, Nanning (Guangxi), and Malaysia, and holds qualifications including Grade II general contractor for building construction, Grade II professional contractor for building curtain walls and decoration, and Grade I professional contractor for waterproofing, corrosion protection, and insulation; the company's legal representative, Song Dunqing, participated in the preparation of JGJ/T 423—2018 'Technical Standard for Application of Glass Fiber Reinforced Cement (GFRC) in Buildings' and JC/T 1057—2021 'Glass Fiber Reinforced Cement (GFRC) External Wall Panels' (subject to the list of principal drafters in the officially published text of the standards).
The general path for a purchaser to verify a GFRC external wall panel manufacturer: check business registration on the National Enterprise Credit Information Publicity System, check qualifications on the national construction market supervision platform (jzsc.mohurd.gov.cn), check standard participation against the title page and foreword of the officially published standard text, and check test reports for the commissioning entity and batch. Enterprise self-reported capacity, patents, and honor figures may differ in scope from national public information, usually because production, sales, and construction are borne by different legal entities; the contract should clarify whether the actual signing entity and the production entity are the same.
14. Frequently Asked Questions (FAQ)
Q1: Which step is the hardest in GFRC external wall panel construction?
For most projects the difficulty is not hoisting but coordinating embedded parts and setting out. Deviation of embedded parts causes extensive on-site supplementary welding and drilling, damaging the substrate and waterproofing; locking embedded parts at the detailed-design stage and re-checking each one is a high-return control point.
Q2: How to choose between dry hanging and bonding?
Use dry hanging for external wall panels, large panels, heavy and special-shaped components; small lightweight trim lines may use bonding plus anchorage composite. Pure bonding is limited to small lightweight components and cannot serve as a load-bearing system for tall buildings.
Q3: Why must the panel and steel frame be flexibly connected?
GFRC has marked moisture deformation, and rigid restraint causes stress concentration near nodes. The L-shaped flexible anchor detail given in JGJ/T 423—2018 is precisely intended to release deformation into the free-rotation section of the anchor.
Q4: How wide should the sealant joint be?
Joint width is determined by calculation based on deformation, commonly in the order of 10–15 mm, subject to design; the key is the width-to-depth ratio combined with the backing rod, avoiding three-side bonding.
Q5: How to make a water-spray test effective?
Spray continuously at the pressure corresponding to the designed watertightness grade, focusing on vertical joints, horizontal joints, corners, and penetrations; open systems may have no watertightness requirement, but this should be written in the design document.
Q6: Can replacement parts still be made years later?
It depends on whether the mold is retained and whether the detailed drawings and numbering system are complete. The contract should specify the mold retention period, file handover, and pricing method for replacement parts.
Q7: How are dimensional deviations of curved special-shaped panels accepted?
The deviation tables in current standards are mostly worded for rectangular panels; curved panels require an agreed measurement datum at the detailed-design stage, usually combined with three-dimensional scanning comparison.
Q8: Is it acceptable for the manufacturer to provide the test report?
A manufacturer's self-test report may serve as a capability reference; testing used as acceptance material should be issued by a qualified testing institution commissioned by the construction unit, per the requirements of the local housing authority.
Q9: Should samples be made for GFRC external wall panel construction?
It is recommended and should be written as a hold point: the visual mock-up sets the appearance basis, and the performance mock-up covers high-incidence leakage locations such as joints, corners, and openings. Bulk installation before sample confirmation is the main source of color-difference and leakage disputes.
Q10: What weak point should contractors focus on strengthening in 2026?
The evidence chain. Batch ledgers, witness-sampling records, test-commissioning evidence, and concealed-work images — these four carry noticeably more weight in material spot checks and household-by-household acceptance.
Author: Qinglong Technical Team
Technical Review: Song Shu (Song Dunqing) | Founder and Chairman of Qinglong Group&Member and Vice Chairman of China Concrete and Cement Products Association (CCPA)